HomeBrowse ProjectsSkyline Tower — Phase 1 MEPF Fit-out
Skyline Tower — Phase 1 MEPF Fit-out
URGENTSeeking: ConsultantHVAC Design & Engineering

Skyline Tower — Phase 1 MEPF Fit-out

KarachiPosted Sep 6, 2026Deadline: Sep 10, 20261 / 20 bids · 19 spots left

Project Description

Skyline Tower — Phase 1 MEPF Fit-out

Turn-key MEPF fit-out covering design, installation coordination, testing, and commissioning.

Project Overview

An 18-storey Grade-A corporate tower with 2 basement levels and an approximate gross floor area of 480,000 sq. ft. The engagement runs from schematic design through testing and commissioning.


HVAC Scope

  • Central chilled-water plant: 2 × 350 TR water-cooled screw chillers with 30% N+1 redundancy, primary/secondary pumping, decoupled loops, and rooftop cooling towers with VFD fans.
  • Air handling: 32 VAV AHUs—typically 2 per floor and 4 per mid-rise tenant floor—with BACnet IP integration to the BMS.
  • Ductwork: Pre-insulated GI ductwork to SMACNA, VAV terminals for open-plan zones at a minimum of 1 per 750 sq. ft., and silencers on all main risers.
  • Ventilation: Dedicated outdoor air at 10% design flow with roof-MAU heat recovery providing at least 65% sensible efficiency.
  • Car-park ventilation: Basement CO monitoring and jet-fan ventilation.
  • BMS: Tridium Niagara AX with Modbus-TCP integration for chillers, pumps, and VAVs.

Electrical Scope

  • LV distribution: 2 × 1,250 kVA transformers with KE and generator ATS changeover, plus 11 kV utility HT to the primary substation.
  • Standby generation: 2 × 800 kVA prime generator sets with N+1 configuration and 24-hour fuel autonomy.
  • Distribution and containment: Main LV panels, floor-level DBs, and dedicated cable-tray routes for power, control, and ELV.
  • Lighting: DALI-controlled LED lighting, occupancy sensors on typical floors, and emergency lighting with a central battery inverter.
  • Small power: Minimum 1 duplex outlet per 60 sq. ft. based on tenant plans.
  • ELV: Dedicated rooms on every floor with access control, CCTV, IP-PA, Cat-6A cabling, and an OS2 fibre spine.

Plumbing Scope

  • Water supply: Ground tank and booster-pump set feeding a 30 m³ roof tank, with zoned cold/hot-water distribution and circulation.
  • Rainwater harvesting: 25 m³ rooftop irrigation tank.
  • Grey-water recycling: Recycled water for WC flushing from floors 2–18.
  • Sewage and waste: Gravity drainage to the basement holding tank with twin-pump ejection to the municipal main.

Fire Protection Scope

  • Sprinklers: Wet system to NFPA 13—light hazard in typical areas and ordinary hazard group 1 in basements and MEP rooms.
  • Fire hose reels: NFPA 14 system with 2 standpipes per floor.
  • Fire alarm: Addressable system with 2 loops per floor, voice evacuation, phased evacuation logic, and a roof-mounted alarm mimic.
  • Fire pumps: Electric duty, diesel standby, and jockey pumps.
  • Gaseous suppression: Inergen or Novec protection for ELV and UPS rooms.

Required Deliverables

  1. Design-freeze package covering basic and detailed design.
  2. Discipline-specific BOQ with at least 3 quotations for each package.
  3. Weekly progress reports and monthly financial reconciliation.
  4. Commissioning and TAB report before handover.
  5. Complete O&M manuals and BIM as-built model in Revit MEP 2025.

Acceptance Criteria

  • HVAC: Air balance within ±10% of design CFM in accordance with AABC.
  • Fire: 100% device functional testing and fire-marshal sign-off.
  • Electrical: Complete LV switchboard type testing and insulation-resistance records for every circuit.
  • Plumbing: 24-hour hydrostatic testing at 1.5× working pressure.

Expected Deliverable Milestones

1

Design freeze — MEPF schematics

2

Long-lead equipment ordered

3

Rough-in complete — Floors 1–6

4

Rough-in complete — Floors 7–18

Required Bid Submission Sections

Your bid must include all of the following sections to be considered.

1

admin

Required
2

experience

Required
3

tech

Required
4

financial

Required
5

timeline

Required
6

review

Required

Bids Received

1 total bids

Bid details are only visible to the project owner.

Tender Status

Open for Bidding

Bidders propose price in bid submission

Sep 11, 2026 – Sep 28, 2026

DeadlineSep 10, 2026
Bids received1 / 20

19 spots remaining

LocationKarachi
SeekingConsultant

Sign in as a Consultant, Contractor, or Service Provider to place a bid

About the Client

KS

Klyron Studio

Verified client
Karachi, Pakistan
Project posted on MEPF Suite
Verified company

Before You Bid

  • Ensure PEC registration is current
  • Prepare company profile document
  • Have BOQ template ready
  • List 3+ similar completed projects
  • Obtain bid security if required